Wednesday, 22 July 2009
Street kids center development on process and more materials are supplied on site drainage system is in the process due to high rainfall.
AHERO EMPIS project is on going
Total number of solidarity groups registered in the BIG by 15th July 2009- 37
Total number of fully registered members by 15th July 2009 - 157 members
Total savings for enterprise promotion by 15th July 2009 -72,800
5Acre Horticultural Farm land preparation is done
Next activities for empis next week include
Fencing of project site
Harrowing of 5 Acre plot
Nursery preparation
Site planning
AHERO EMPIS project is on going
Total number of solidarity groups registered in the BIG by 15th July 2009- 37
Total number of fully registered members by 15th July 2009 - 157 members
Total savings for enterprise promotion by 15th July 2009 -72,800
5Acre Horticultural Farm land preparation is done
Next activities for empis next week include
Fencing of project site
Harrowing of 5 Acre plot
Nursery preparation
Site planning
Monday, 13 July 2009
STREET KIDS CENTER STRUCTURAL DEVELOPMENT
The Center Sanitation Facility is in the proceess as specified by the Kisumu City Council EngineersThis will be completed and ready for inspection on Friday 17th July 2009 according to constructors on siteThe materials for the main foundation is being delivered to the site from today 13th July .Site store has been built and security officers put to ensure safety of the materials delivered.The team from KIWASCO is inspecting the water lines passing on site tomorrow to avoid busting pipes running to the city center.
The Center Sanitation Facility is in the proceess as specified by the Kisumu City Council EngineersThis will be completed and ready for inspection on Friday 17th July 2009 according to constructors on siteThe materials for the main foundation is being delivered to the site from today 13th July .Site store has been built and security officers put to ensure safety of the materials delivered.The team from KIWASCO is inspecting the water lines passing on site tomorrow to avoid busting pipes running to the city center.
STREET KIDS CENTER STRUCTURAL DEVELOPMENT
The Center Sanitation Facility is in the proceess as specified by the Kisumu City Council Engineers
This will be completed and ready for inspection on Friday 17th July 2009 according to constructors on site
The materials for the main foundation is being delivered to the site from today 13th July .Site store has been built and security officers put to ensure safety of the materials delivered.
The team from KIWASCO is inspecting the water lines passing on site tomorrow to avoid busting pipes running to the city center.
The Center Sanitation Facility is in the proceess as specified by the Kisumu City Council Engineers
This will be completed and ready for inspection on Friday 17th July 2009 according to constructors on site
The materials for the main foundation is being delivered to the site from today 13th July .Site store has been built and security officers put to ensure safety of the materials delivered.
The team from KIWASCO is inspecting the water lines passing on site tomorrow to avoid busting pipes running to the city center.
Monday, 6 July 2009
CHIGA EMPIS CENTRE
The business plan for the center is ready for sharing
The center has 5 distinct components namely:
The business plan for the center is ready for sharing
The center has 5 distinct components namely:
- Community bank for savings mobilization and enterprise promotion to the poor
- Farmers Field School (school without walls) for training farmers on good agricultural practices and food security
- Community information center for the youth
- Community based collection and marketing center (for value addition and collective marketing)
- Orphans support center (for education,nutrition and health support)
Street Kisds Engineering Project Progress June-July 2008
The first phase of the CENTRE has been funded by VCAA and partners, on 26th June.
Structural designs done and approval by the Kisumu City Council in progress after site visit by the city council planners and surveyors
Ground leveling in progress and foundation of the training center starts this week.
Container carrying engineering tools from Amsterdam arrived in Kisumu on 3rd July2008 carrying mechanical engineering equipment,tools and computers.
Street kids mechanical training curriculum development for both intermediate and certificate in progress
The first phase of the CENTRE has been funded by VCAA and partners, on 26th June.
Structural designs done and approval by the Kisumu City Council in progress after site visit by the city council planners and surveyors
Ground leveling in progress and foundation of the training center starts this week.
Container carrying engineering tools from Amsterdam arrived in Kisumu on 3rd July2008 carrying mechanical engineering equipment,tools and computers.
Street kids mechanical training curriculum development for both intermediate and certificate in progress
Friday, 3 July 2009
New sponsor: Turing Foundation

We are very happy and grateful to announce that Turing Foundation is one of the new sponsors of Streetkids Engineering. Due to their support we are able to build the class rooms at the first floor.
The Turing Foundation is a private charity based in the Netherlands.
They strive to offer children and young people the kind of education that can help them structurally, encourage their independence and autonomy, and enable them to contribute to their communities.
The Turing Foundation regards education as a means to offer people new opportunities in their lives in a constructive, structural and respectful way. Moreover, education benefits not only the individual, but also his environment and society as a whole. It can be seen as a sustainable method of poverty reduction.
Subscribe to:
Posts (Atom)