Saturday, 29 August 2009

TRAINING CENTER CONSTRUCTION PROGRESS

CONSTRUCTION PROGRESS BY END OF AUGUST

The foundation of the Building is done
The garage floor (slab) is done
Water source for construction established- Bore hole dug on site
Sanitation facility done on site
The garage wall is almost done, currently the continuous ventilations are manufactured by order and they will be supplied on site by 2nd Sep
Preparation for completing the garage roof is at an advance stage and most of the materials for the stage is ready.We hope to do it any time from 5th Sep 2009.The part will take 1 week and a
celebration will be hosted immediately its done as an appreciation for the good job done by fundis and our supporting agencies

Thursday, 6 August 2009

Street Kids Centre Construction Work In Kisumu-Kenya

The Foundation is done and curing is almost through

Site store in place for keeping construction materials

Kisumu Mater and Serage company has inspected the site and recomended water conection in the site for the construction,All plans have been approved for water connection and payment done.

External sanitation facility is a health requirement immediately and the construction of a temporary one almost complete.The main sanitation facility devlopment was pushed to phase two