CONSTRUCTION PROGRESS BY END OF AUGUST
The foundation of the Building is done
The garage floor (slab) is done
Water source for construction established- Bore hole dug on site
Sanitation facility done on site
The garage wall is almost done, currently the continuous ventilations are manufactured by order and they will be supplied on site by 2nd Sep
Preparation for completing the garage roof is at an advance stage and most of the materials for the stage is ready.We hope to do it any time from 5th Sep 2009.The part will take 1 week and a
celebration will be hosted immediately its done as an appreciation for the good job done by fundis and our supporting agencies
The foundation of the Building is done
The garage floor (slab) is done
Water source for construction established- Bore hole dug on site
Sanitation facility done on site
The garage wall is almost done, currently the continuous ventilations are manufactured by order and they will be supplied on site by 2nd Sep
Preparation for completing the garage roof is at an advance stage and most of the materials for the stage is ready.We hope to do it any time from 5th Sep 2009.The part will take 1 week and a
celebration will be hosted immediately its done as an appreciation for the good job done by fundis and our supporting agencies